Local Government Solar Arrays in Garfield County
Garfield Clean Energy member governments
Town of Parachute
22.9 kilowatts at 3 facilities
- Town Hall: 9.7 kW, 2010
- Water Treatment Plant: 9.6 kW, 2010
- I-70 Rest Area Solar Flowers: 3.6 kW, 2010
City of Rifle
2,775 kilowatts at 13 facilities
- Water Treatment Plant pump station: 600 kW, 2008
- Wastewater Treatment Plant: 1,720 kW, 2009 (largest government array in Garfield County)
- Taughenbaugh pump station: 42 kW, 2013
- South pump station: 15 kW, 2013
- Police Department & Courts: 10 kW, 2010
- Police Department & Courts: 130 kW, 2013
- Parks Maintenance Building: 9.9 kW, 2010
- Parks Maintenance Building: 55 kW, 2013
- Operations and Maintenance Shop: 10 kW, 2010
- Operations and Maintenance Shop: 24 kW, 2014
- City Hall Parking Structure: 140.5 kW, 2014
- Rifle Ball Field, 9.4 kW, 2013
- Rosehill Cemetery, 9.6 kW, 2013
Town of Silt
261 kilowatts at 4 facilities
- Town Hall: 9 kW, 2010
- Wastewater Treatment Plant: 9 kW, 2010
- Senior Housing: 9 kW, 2010
- Water Treatment Plant: 234 kW, 2015
Town of New Castle
70.5 kilowatts at 1 facility
- Public Works: 70.5 kW, 2009
City of Glenwood Springs
20.5 kilowatts at 1 facility
- Community Center: 20.5 kW, 2010
Town of Carbondale
165 kilowatts at 6 facilities
- Town Hall: 4 kW, 2004 (1st government array in Garfield County)
- Sopris Park Shelter: 6.4 kW, 2006
- Recreation Center: 51.8 kW, 2008
- Roaring Fork Water Treatment Plant: 87 kW, 2013
- Public Works Shop: 18.6 kW, 2013
- Third Street Center: 105.5 kW, 2009, 2010, 2013
Garfield County
101.2 kilowatts at 1 facility
- Fairgrounds Riding Arena: 101.2 kW, 2011
Colorado Mountain College
102 kilowatts at 1 facility
- Rifle Campus: 102 kW, 2011 (CMC student installation)
Roaring Fork Transportation Authority
618 kilowatts at 1 facility
- Sunny Side Array: 618 kW share, 2015 (1st government-owned off-site solar)
Other Local Governments in Garfield County
Garfield County Library District
132.6 kilowatts at 5 facilities
- Parachute Branch: 9.6 kW, 2010
- Rifle Branch: 53 kW, 2010
- New Castle: 10 kW, 2012 (CMC student installation)
- Silt Branch: 30 kW, 2013 (CMC student installation)
- Carbondale: 30 kW, 2014 (CMC student installation)
Battlement Mesa Metro District
435 kilowatts at 1 facility
- Water Treatment Plant: 435 kW, 2015
Roaring Fork School District Re-1
719 kilowatts at 2 facilities
- Roaring Fork High School: 379 kW, 2015
- Riverview Elementary: 340 kW, 2018